验收防水材料的施工的标准 |
一般情况只是对管子的根部或者屋面部分山东防水材料的施工,进行抽样浇水处理,抽取的数量要超出屋面泛水的三分之一,浇水的时间建议不要少于一个小时,如果没有渗漏就算合格。但是若出现渗漏情况,就要抽取双倍的数量进行试验,若还是有渗漏的情况,就应该全部浇水进行试验。
A级防火保温材料
The general situation of the construction is the root or part of Shandong roofing waterproof materials, sampling watering treatment, extraction quantity to exceed the roof flashing 1/3, watering time not less than one hour, if there is no leakage even qualified. However, if there is leakage, it is necessary to extract the number of double test, if there is leakage, it should be all water for testing.
一般墙面山东防水材料处理的高度建议不低于20cm,*下端需要用细石混凝土做墙垫,墙垫的高度不能小于100mm,这是对于墙面防水的*基础要求。对于墙体防水的验收,建议采取淋水试验,在3到4分钟不间断的喷淋中,如果墙面不出现渗透现象就算合格。
General wall of Shandong waterproof material treatment is highly recommended not less than 20cm, the lower end of the need to use fine stone concrete wall pad, the height of the wall mat can not be less than 100mm, which is the most basic requirements for wall waterproofing. For the acceptance of the wall, it is recommended to take the water test, in 3 to 4 minutes of continuous spray, if the wall does not appear even if the penetration phenomenon.
一般在卫生间的山东防水材料施工完毕后,先将卫生间的下水口堵死,然后在门口位置垒一个15cm高的坎,*后再在卫生间灌入15cm左右的水。验收时间 是在24个小时之后,这个时候再去检查四周墙面以及地面是否出现渗漏现象,时间一定要把握好,这是保证卫生间山东防水材料施工能否有效的关键之处。
General in the bathroom after Shandong construction of waterproof material, the sewer blocked the toilet, and then at the gate location to base a 15cm high ridge, then poured into the toilet in the water 15cm. Acceptance time is after 24 hours, this time to check the surrounding walls and whether the ground leakage phenomenon, must grasp the time |
|
|
|
|
|
|
|